BC Hydro Underground Utility Construction on 1800-1900 Block of W 7th Avenue
Location:
Both Sides of 1800-1900 Block of W 7th Avenue From Burrard Street to Maple Street.
Expected Schedule:
Recurring schedule as follows:
- Aug 31, 2026 - Oct 30, 2026; Weekdays; 7:00 AM - 8:00 PM
- Nov 1, 2026 11:00 PM - Nov 13, 2026 10:59 PM; Weekdays; 7:00 AM - 8:00 PM
- Nov 15, 2026 11:00 PM - Nov 27, 2026 10:59 PM; Weekdays; 7:00 AM - 8:00 PM
Except:
- Does not occur Nov 10, 2026 11:00 PM (Stat Holiday)
- Does not occur Nov 17, 2026 11:00 PM (Conflicting work on W 6th Ave)
- Does not occur Nov 18, 2026 11:00 PM (Conflicting work on W 6th Ave)
Status:
Approved
Description:
Reduced lanes on Both Sides of 1800-1900 Block of W 7th Avenue to facilitate underground utility construction.
Parking meters to be hood: B7-18-01/03/05/07/09/11/13
WO# W02556589-06 / 457-U07-03432