Placeholder - Mt Pleasant Substation Transformer Install
Location:
Expected Schedule:
Jul 15, 2026 - Mar 31, 2027
Status:
Approved
Description:
Please confirm with Catherine Chow for any specific questions. For Transformer Delivery - FULL Closure of W. 6th from Yukon to Columbia for 3 days in late August. (Including Alberta north and south of W. 6th).
Update Sep 16, 2026 - Laydown areas established for this project. The laydown area is expected to remain in place until early next year