City of Vancouver - Road Ahead - Event Details
Event:
Kaslo Street Sewer Main Upgrade
Location:
Kaslo St from E 28th Ave to E 29th Ave
Expected Schedule:
Apr 16, 2018 - Jun 29, 2018; Weekdays; 7:00 AM - 3:30 PM
Status:
Under Construction
Description:
City crews will be upgrading the sewer main along Kaslo St between E 28th Ave and E 29th Ave. The anticipated duration of underground sewers work to take is approximately 3 weeks. Surface restoration will follow. The general working hours will be 7am to 3:30pm, Monday to Friday, unless overtime is necessary due to unforeseen circumstances. During construction, traffic along Kaslo St will be closed. Street parking will be temporarily removed and will be normalized when it is safe to do so. Residents access will be maintained.
Posted:
Apr 12, 2018
Updated:
May 11, 2018 3:07 PM

City Contact:
Gwenda Sulem
604.873.7235