Event:
Bute St Test Holes (for Haro St Water Main Replacement Project)
Location:
Bute St from Haro St to W Pender St
Expected Schedule:
Apr 12, 2018 - May 14, 2018; Weekdays; 7:00 AM - 3:30 PM
Status:
Under Construction
Description:
City crews have had begun the test holes along Bute St between Haro St and W Pender St. The anticipated duration of work is approximately 20 days. The general working hours are Monday to Friday, 7am to 3:30pm, unless overtime is necessary due to unforeseen circumstances. Traffic along Bute St will be reduced to one lane in each direction. Parking will be restricted to accommodate construction equipment or work trailers. Restrictions will change during the course of this project and will be removed as soon as they aren't needed. Access to residents and businesses will be maintained at all times.
Posted:
Apr 12, 2018
Updated:
May 11, 2018 2:35 PM

City Contact:
Brandon Hildebrandt
604.871.6276