1800 Quebec Street between 3rd Avenue and the lane north.
Expected Schedule:
Apr 22, 2025 - May 9, 2025
Status:
Under Construction
Description:
City's external contractor will be working on the east side of Quebec Street between 3rd Avenue and the lane north to construct a protected, raised bike lane, and the associated roadway upgrades. Construction is scheduled to take place during normal working hours, weekdays from April 22 to May 9, including localized excavation, gravel base compaction, concrete works, utility adjustments, targeted paving and road marking restoration.