City of Vancouver - Road Ahead - Event Details
Event:
E 5th Ave Water Main Replacement Project
Location:
E 5th Ave between Lakewood Dr and Garden Dr
Expected Schedule:
Sep 11, 2017 - Oct 27, 2017; Weekdays; 7:00 AM - 3:30 PM
Status:
Under Construction
Description:
City crews have begun the water main construction along E 5th Ave from Lakewood Dr to Garden Dr. The anticipated duration of work is 6 weeks. The general working hours 7am to 3;30pm Monday to Friday unless overtime is required due to unforeseen circumstances. Through traffic and street parking will be closed in the project area where crews are working. However, crews will do their best to provide residential parking as possible after working hours. Occasionally, you may notice cloudy water as a result of the construction activities. This cloudiness is not a health concern and should only last a short period of time. In the event that you do experience cloudy water, the City recommends that you run your taps for up to 30 minutes or until the cloudiness dissipates.
Posted:
Sep 8, 2017
Updated:
Sep 29, 2017 11:35 AM

City Contact:
Brandon Hildebrandt
604.871.6276